Natural gasNatural Gas Fired Combined Cycle⛽ Dual-fuelPJMBA: PJM
Nameplate1,153MWSummer 1,136 MW
Generators8in service
Net generation6,015GWh12 mo to Aug 2026
Capacity factor60%gas/coal/oil units, summer MW
Heat rate8,164Btu/kWhfossil units, electric fuel, HHV
First online2002Runs as baseload

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600GWh200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202560.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
7,5008,0008,5009,0009,500200520102015202020258,164 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2003634.59.0%9,480
2004919.69.6%8,605
20051,291.713.5%8,310
20061,00910.5%8,347
20071,76518.4%8,170
20081,321.413.3%8,391
20091,320.413.3%8,269
20102,791.528.2%8,088
20114,105.341.5%8,106
20125,811.758.6%8,022
20134,869.849.2%8,079
20144,70347.3%8,106
20155,327.353.6%8,136
20165,34353.6%8,102
20174,797.748.3%8,096
20184,159.641.9%8,088
20194,72247.5%8,135
20205,602.156.2%8,070
20213,497.135.2%8,071
20224,361.843.9%8,024
20235,991.560.2%8,141
20245,938.159.5%8,074
20255,821.258.5%8,140

Fuel capability

Gas-fired turbines (CT/GT/CA/CS) that can also burn liquid fuel. EIA-860 Schedule 3 for capability, EIA-923 for actual burn.
StatusLikely still dual fuel
Liquid fuel burned · 36 mo1,481,744 MMBtu
Last month with liquid burnFeb 2026
Switch while operatingYes
Net summer MW on gas1,134
Net summer MW on oil1,134
Time gas → oilup to 6 h (EIA 6H)
Time oil → gasup to 6 h (EIA 6H)

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CTG1Natural Gas Fired Combined CycleCT127125Dec 2002Operating—coming soon
CTG2Natural Gas Fired Combined CycleCT127125Dec 2002Operating—coming soon
CTG3Natural Gas Fired Combined CycleCT127125Dec 2002Operating—coming soon
CTG5Natural Gas Fired Combined CycleCT127125Jan 2003Operating—coming soon
CTG6Natural Gas Fired Combined CycleCT127125Feb 2003Operating—coming soon
CTG7Natural Gas Fired Combined CycleCT127125Apr 2003Operating—coming soon
STG4Natural Gas Fired Combined CycleCA195.5193May 2003Operating—coming soon
STG8Natural Gas Fired Combined CycleCA195.5193Dec 2003Operating—coming soon

Owner / operator

Operator: Calpine Bethlehem LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Calpine Bethlehem LLC100.0%1,153 MW

Nearby plants

Within 80 km.
EDF Saucon Valley3 MW5.4 km
TalenEnergy Martin Creek LLC Allentownretired12 km
UE-2202PA, LLC2 MW13.2 km
Uniqlo Phase 1 Solar Farm3 MW13.3 km
Milford Solar Farm (NJ) LLC8 MW13.4 km
Holland Solar Farm7 MW13.5 km