← Back to map

Montgomery Creek Hydro

Shasta County, California · EIA plant ID 55009 · Operator: Central Rivers Power US, LLC
HydroConventional HydroelectricCAISOBA: CISO
Nameplate3MWSummer 3 MW
Generators1in service
Net generation9GWh12 mo to Dec 2025
Capacity factor41%hydro units, summer MW
Heat rate—thermal plants only
First online1987

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.511.5GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202540.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20018.537.4%—
20029.441.4%—
200312.153.1%—
20040.52.2%—
200510.546.3%—
200611.651.1%—
20075.925.7%—
20086.327.6%—
20096.427.9%—
201012.454.4%—
201111.450.2%—
20126.528.6%—
20134.921.7%—
20144.318.9%—
20151.87.9%—
201611.148.8%—
201710.445.7%—
20186.427.9%—
20191043.8%—
20203.615.9%—
2021313.2%—
20223.716.2%—
20238.437.0%—
202410.144.4%—
20259.240.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Conventional HydroelectricHY2.62.6Jan 1987Operating—coming soon

Owner / operator

Operator: Central Rivers Power US, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Central Rivers Power US, LLC100.0%3 MW

Nearby plants

Within 80 km.
Cove Hydroelectric5 MW2.8 km
Pit 7110 MW2.9 km
Roaring Creek Water Power2 MW4 km
Hatchet Creek Project7 MW4.3 km
Pit 679 MW9 km
Hatchet Ridge Wind Project101 MW14.1 km