← Back to map

Pine Tree Acres

Macomb County, Michigan · EIA plant ID 54989 · Operator: EPP Renewable Energy
OtherLandfill GasMISOBA: MISO
Nameplate9MWSummer 9 MW
Generators9in service
Net generation56GWh12 mo to Aug 2026
Capacity factor73%other units, summer MW
Heat rate—thermal plants only
First online1998

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0246GWh2002200420062008201020122014201620182020202220242026

Capacity factor by year

Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%50%100%2005201020152020202572.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200234.297.5%—
200334.695.5%—
200447.496.3%—
200547.596.8%—
200647.296.3%—
200725.151.1%—
20084693.4%—
200946.594.8%—
201054.994.0%—
201171.692.8%—
201269.189.3%—
201370.391.2%—
201472.493.9%—
201572.393.8%—
201672.193.2%—
201770.991.9%—
201868.188.3%—
201971.993.3%—
202071.192.0%—
202165.284.6%—
202268.188.4%—
202365.685.0%—
202467.887.7%—
202560.478.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Landfill GasIC0.80.8Jun 1998Operating—coming soon
GEN2Landfill GasIC0.80.8Jun 1998Operating—coming soon
GEN3Landfill GasIC0.80.8Jun 1998Operating—coming soon
GEN4Landfill GasIC0.80.8Jun 1998Operating—coming soon
GEN5Landfill GasIC0.80.8Jun 1998Operating—coming soon
GEN6Landfill GasIC0.80.8Dec 2003Operating—coming soon
GEN7Landfill GasIC0.80.8Dec 2003Operating—coming soon
GEN8Landfill GasIC1.61.6Sep 2010Operating—coming soon
GEN9Landfill GasIC1.61.6Sep 2010Operating—coming soon

Owner / operator

Operator: EPP Renewable Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
EPP Renewable Energy100.0%9 MW

Nearby plants

Within 80 km.
Pine Tree Acres WM LFGTE13 MW0.1 km
Belle River1,664 MW20.6 km
Blue Water Renewables Inc3 MW20.9 km
DTE East China LLC358 MW20.9 km
Blue Water Energy Center1,267 MW21.9 km
Cargill Salt4 MW22.2 km