Androscoggin County, Maine · EIA plant ID 52171 · Operator: KEI (Maine) Power Management (III) LLC
Nameplate1MWSummer 1 MW
Generators1in service
Net generation4GWh12 mo to Dec 2025
Capacity factor45%hydro units, summer MW
Heat rate—thermal plants only
First online1987
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2001 | 3.1 | 24.5% | — |
| 2002 | 4 | 32.1% | — |
| 2003 | 4.9 | 39.1% | — |
| 2004 | 4.9 | 38.8% | — |
| 2005 | 7 | 55.7% | — |
| 2006 | 7.5 | 60.2% | — |
| 2007 | 4.9 | 40.0% | — |
| 2008 | 8 | 64.6% | — |
| 2009 | 7.4 | 60.7% | — |
| 2010 | 4 | 45.4% | — |
| 2011 | 6.6 | 74.9% | — |
| 2012 | 6.1 | 69.7% | — |
| 2013 | 6.9 | 79.2% | — |
| 2014 | 5.2 | 59.7% | — |
| 2015 | 3.7 | 41.7% | — |
| 2016 | 4.1 | 46.7% | — |
| 2017 | 5 | 56.7% | — |
| 2018 | 4.3 | 49.1% | — |
| 2019 | 4.2 | 48.1% | — |
| 2020 | 4.8 | 54.3% | — |
| 2021 | 3.9 | 44.9% | — |
| 2022 | 4.6 | 53.0% | — |
| 2023 | 6.6 | 75.5% | — |
| 2024 | 4.7 | 53.0% | — |
| 2025 | 4 | 45.2% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| GEN1 | Conventional Hydroelectric | HY | 1 | 1 | May 1987 | Operating | — | coming soon |
Owner / operator
Operator: KEI (Maine) Power Management (III) LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| KEI (Maine) Power Management (III) LLC | 100.0% | 1 MW |
Nearby plants
Within 80 km.
| Barker Lower | 2 MW | 0 km |
| Upper Androscoggin | 2 MW | 1.4 km |
| Charles E Monty | 28 MW | 1.6 km |
| MMWAC Resource Recovery Facility | 5 MW | 3.3 km |
| Deer Rips | 7 MW | 5.7 km |