← Back to map

Toledo Ref Power Recovery Train

Lucas County, Ohio · EIA plant ID 50965 · Operator: Toledo Refining Company
CoalPetroleum CokePJMBA: PJM
Nameplate6MWSummer 6 MW
Generators1in service
Net generation0GWh12 mo to Aug 2026
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online1986

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02468GWh200120042007200920112014201620182020202220242026

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200121.9——
200227.2——
20040——
200611.3——
20072.3——
2008106.7——
200993.6——
201089.6——
20110.3——
20122.6——
20140.2——
20159——
20169.9——
20170.3——
201810.2——
20193.6——
20200.3——
20210——
20220——
20231.4——
20240.6——
20250——

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Petroleum CokeOT66Jun 1986Operating—coming soon

Owner / operator

Operator: Toledo Refining Company. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Toledo Refining Company100.0%6 MW

Nearby plants

Within 80 km.
Owens Corning Headquarters2 MW3 km
PNA Rossford Solar Array1 MW4.8 km
Anthony Wayne Solar #12 MW5.9 km
Oregon Clean Energy Center1,062 MW6.4 km
Bay View Cogeneration Facility12 MW6.4 km
Bay View Backup Power Facility12 MW6.4 km