← Back to map

Wheelabrator North Andover

Essex County, Massachusetts · EIA plant ID 50877 · Operator: Wheelabrator Environmental Systems
OtherMunicipal Solid WasteISONEBA: ISNE
Nameplate40MWSummer 30 MW
Generators1in service
Net generation246GWh12 mo to Aug 2026
Capacity factor94%other units, summer MW
Heat rate—thermal plants only
First online1985

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0102030GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020202593.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2001234.681.2%—
2002230.579.7%—
2003242.283.8%—
2004238.282.2%—
2005231.788.2%—
2006238.390.7%—
2007229.187.2%—
2008236.689.8%—
200924191.7%—
2010241.491.9%—
2011242.892.4%—
2012238.790.6%—
2013248.394.5%—
2014242.292.2%—
2015249.695.0%—
201625094.9%—
2017242.192.1%—
2018240.891.6%—
2019218.483.1%—
2020229.987.3%—
2021232.888.6%—
2022228.887.1%—
202323890.6%—
2024239.991.0%—
202524091.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Municipal Solid WasteST40.330May 1985Operating—coming soon

Owner / operator

Operator: Wheelabrator Environmental Systems. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Wheelabrator Environmental Systems100.0%40 MW

Nearby plants

Within 80 km.
Bradford Solar5 MW3.6 km
Covanta Haverhill46 MW4.3 km
Lawrence Hydroelectric Associates15 MW4.6 km
Methuen Landfill1 MW4.8 km
Haverhill Solar Power Project1 MW6.6 km
Kearsarge Haverhill5 MW6.8 km