← Back to map

Forks of Butte Hydro Project

Butte County, California · EIA plant ID 50350 · Operator: HYPOWER INC
HydroConventional HydroelectricCAISOBA: CISO
Nameplate15MWSummer 15 MW
Generators1in service
Net generation58GWh12 mo to Dec 2025
Capacity factor46%hydro units, summer MW
Heat rate—thermal plants only
First online1992

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02.557.510GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%2005201020152020202545.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200131.527.1%—
200235.730.6%—
200357.949.7%—
200439.330.8%—
200552.941.7%—
200660.547.6%—
200719.715.5%—
200827.721.7%—
200931.424.8%—
201063.550.0%—
201156.344.3%—
201232.225.3%—
201325.620.2%—
201421.617.0%—
201516.312.8%—
201651.340.3%—
201761.248.1%—
201829.823.4%—
201953.342.0%—
202014.911.7%—
202113.810.9%—
20229.97.8%—
202341.933.0%—
202465.951.8%—
202558.245.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Conventional HydroelectricHY14.514.5Mar 1992Operating—coming soon

Owner / operator

Operator: HYPOWER INC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
HYPOWER INC100.0%15 MW

Nearby plants

Within 80 km.
De Sabla18 MW0 km
Toadtown2 MW4.2 km
Centerville PH6 MW9.2 km
Cresta74 MW19.6 km
Lime Saddleretired19.7 km
Poe143 MW21.4 km