Natural gasNatural Gas Fired Combustion TurbineERCOTBA: ERCO
Nameplate7MWSummer 7 MW
Generators2in service
Net generation19GWh12 mo to Dec 2025
Capacity factor31%gas/coal/oil units, summer MW
Heat rate4,904Btu/kWhfossil units, electric fuel, HHV
First online1986Runs as intermediate

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
01234GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202531.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
4,0005,0006,0007,0008,000200520102015202020254,904 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200142.369.0%5,301
200221.935.7%5,668
200329.147.4%7,999
200432.352.5%5,621
200530.350.2%5,621
200628.246.6%5,621
200731.151.4%5,621
200824.540.4%5,621
200928.146.5%5,621
201026.744.2%5,621
201122.537.3%5,621
201222.637.3%5,621
201327.445.4%5,621
20145.99.8%5,621
201520.433.7%5,621
20165.99.8%4,904
201726.644.0%4,904
201828.847.7%4,904
201919.632.4%4,904
20208.914.7%4,904
202120.634.0%4,904
202220.433.8%4,904
202318.630.8%4,904
202417.729.2%4,904
20251931.4%4,904

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Natural Gas Fired Combustion TurbineGT3.13.1Jan 1986Operating (Standby / backup)—coming soon
GEN2Natural Gas Fired Combustion TurbineGT3.83.8Feb 1989Operating—coming soon

Owner / operator

Operator: Rice University. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Rice University100.0%7 MW

Nearby plants

Within 80 km.
The Methodist Hospital, Gas Turbine5 MW1.4 km
TECO CHP-198 MW2 km
OTHERTraditionBuffalo1 MW5.1 km
HEB007791 MW5.9 km
Crockett BESS10 MW6.4 km