← Back to map

Box Canyon

Pend Oreille County, Washington · EIA plant ID 3891 · Operator: PUD No 1 of Pend Oreille County
HydroConventional HydroelectricBA: AVA
Nameplate90MWSummer 90 MW
Generators4in service
Net generation460GWh12 mo to Dec 2025
Capacity factor58%hydro units, summer MW
Heat rate—thermal plants only
First online1955

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02040GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202558.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2001363.354.0%—
2002399.859.4%—
2003435.364.7%—
2004482.171.5%—
2005446.666.4%—
2006448.766.7%—
2007453.667.4%—
2008406.860.3%—
2009438.965.2%—
2010392.458.3%—
2011403.760.0%—
2012375.751.3%—
2013415.154.7%—
201443557.3%—
2015507.264.3%—
2016487.461.7%—
2017352.744.7%—
2018441.656.0%—
2019460.858.5%—
2020448.756.8%—
2021475.160.3%—
2022450.257.1%—
2023383.548.6%—
2024464.158.7%—
2025459.858.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY22.522.5Jun 1955Operating—coming soon
2Conventional HydroelectricHY22.522.5Jul 1955Operating—coming soon
3Conventional HydroelectricHY22.522.5Aug 1955Operating—coming soon
4Conventional HydroelectricHY22.522.5Aug 1955Operating—coming soon

Owner / operator

Operator: PUD No 1 of Pend Oreille County. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
PUD No 1 of Pend Oreille County100.0%90 MW

Nearby plants

Within 80 km.
Boundary1,160 MW23.5 km
Sheep Creek Hydro2 MW33.2 km
Meyers Falls2 MW51.4 km
Kettle Falls Generating Station58 MW53.9 km
Smith Falls Hydro Project38 MW66 km
Albeni Falls42 MW73.6 km