Rocky Reach

Chelan County, Washington · EIA plant ID 3883 · Operator: PUD No 1 of Chelan County
HydroConventional HydroelectricBA: CHPD
Nameplate1,349MWSummer 1,254 MW
Generators11in service
Net generation6,398GWh12 mo to Aug 2026
Capacity factor58%hydro units, summer MW
Heat rate—thermal plants only
First online1961

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600800GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202558.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20014,30138.4%—
20025,841.552.1%—
20035,27247.0%—
20045,425.548.3%—
20055,756.951.4%—
20066,148.254.9%—
20076,303.755.4%—
20085,779.650.6%—
20095,341.648.6%—
20105,070.846.2%—
20117,168.265.3%—
20126,953.363.1%—
20136,360.957.9%—
20146,293.857.3%—
20155,948.254.1%—
20166,069.455.1%—
20176,141.155.9%—
20186,287.857.2%—
20195,020.845.7%—
20205,896.253.5%—
20215,728.952.2%—
20226,448.558.7%—
20235,001.545.5%—
20244,901.144.5%—
20255,241.147.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
C-1Conventional HydroelectricHY114104.9Jun 1961Operating—coming soon
C-10Conventional HydroelectricHY137.8129.9Jan 1974Operating—coming soon
C-11Conventional HydroelectricHY137.8129.9Feb 1974Operating—coming soon
C-2Conventional HydroelectricHY114104.9Jun 1961Operating—coming soon
C-3Conventional HydroelectricHY114104.9Jun 1961Operating—coming soon
C-4Conventional HydroelectricHY114104.9Aug 1961Operating—coming soon
C-5Conventional HydroelectricHY114104.9Aug 1961Operating—coming soon
C-6Conventional HydroelectricHY114104.9Aug 1961Operating—coming soon
C-7Conventional HydroelectricHY114104.9Sep 1961Operating—coming soon
C-8Conventional HydroelectricHY137.8129.9Aug 1973Operating—coming soon
C-9Conventional HydroelectricHY137.8129.9Nov 1973Operating—coming soon

Owner / operator

Operator: PUD No 1 of Chelan County. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
PUD No 1 of Chelan County100.0%1,349 MW