← Back to map

Grayson

Los Angeles County, California · EIA plant ID 377 · Operator: City of Glendale - (CA)
Natural gasBatteriesNatural Gas Fired Combustion TurbineNatural Gas Internal Combustion EngineOTHERBA: LDWP

×244 MW natural gas retired since 2020 (latest May 2023)

Nameplate189MWSummer 178 MW
Generators5in service
Net generation14GWh12 mo to Aug 2026
Capacity factor3%gas/coal/oil units, summer MW
Heat rate9,686Btu/kWhfossil units, electric fuel, HHV
First online2004Runs as peaking

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02040GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%200520102015202020253.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
8,00010,00012,00014,000200520102015202020259,686 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2001403.6——
2002176.5——
2003160.34.6%14,481
2004194.15.6%13,458
2005186.75.1%13,237
20061693.9%14,362
2007177.37.3%13,852
2008203.37.9%12,291
2009180.511.5%12,559
2010186.99.3%12,799
2011171.88.0%12,848
2012177.87.4%13,110
20131626.6%13,076
2014159.36.6%13,591
2015169.46.6%12,920
2016144.64.4%13,508
2017145.24.4%12,825
2018140.85.7%13,422
201980.53.9%13,784
2020116.15.5%13,125
2021146.16.5%13,193
202281.93.6%13,948
202332.73.5%11,469
20244711.1%10,364
202514.43.4%10,849

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
10BatteriesBA7575Aug 2026Operating—coming soon
11Natural Gas Internal Combustion EngineIC18.818.4Aug 2026Operating—coming soon
12Natural Gas Internal Combustion EngineIC18.818.4Aug 2026Operating—coming soon
13Natural Gas Internal Combustion EngineIC18.818.4Aug 2026Operating—coming soon
9Natural Gas Fired Combustion TurbineGT57.448Jan 2004Operating—coming soon
1Natural Gas Fired Combined CycleCA2019Jul 1977Retired May 2023—coming soon
2Natural Gas Fired Combined CycleCA2019Jul 1977Retired May 2023—coming soon
3Natural Gas Steam TurbineST2318Dec 1953Retired Mar 2023—coming soon
4Natural Gas Steam TurbineST5040Sep 1959Retired May 2023—coming soon
5Natural Gas Steam TurbineST5040Nov 1964Retired Apr 2023—coming soon
6Natural Gas Fired Combustion TurbineGT2215Apr 1972Retired Mar 2004—coming soon
7Natural Gas Fired Combustion TurbineGT3120Feb 1974Retired Nov 2002—coming soon
8ANatural Gas Fired Combined CycleCT25.426Jul 1977Retired Apr 2023—coming soon
8BCNatural Gas Fired Combined CycleCT55.146Jul 1977Retired May 2023—coming soon

Owner / operator

Operator: City of Glendale - (CA). Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
City of Glendale - (CA)100.0%189 MW

Nearby plants

Within 80 km.
Glendale Battery Energy Storage System2 MW0.9 km
Toyon Power Station1 MW2.7 km
Olive110 MW4.1 km
Lake One61 MW4.1 km
Magnolia Power Project388 MW4.3 km
Kaiser - LA5 MW6.5 km