← Back to map

Pickwick Landing Dam

Hardin County, Tennessee · EIA plant ID 3415 · Operator: Tennessee Valley Authority
HydroConventional HydroelectricBA: TVA
Nameplate240MWSummer 244 MW
Generators6in service
Net generation1,295GWh12 mo to Dec 2025
Capacity factor60%hydro units, summer MW
Heat rate—thermal plants only
First online1938

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
050100150GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202560.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20011,158.565.0%—
20021,067.249.0%—
20031,485.668.2%—
20041,326.357.9%—
20051,208.553.3%—
20061,04846.2%—
2007625.227.4%—
2008884.338.6%—
20091,402.564.0%—
20101,02848.0%—
20111,240.658.0%—
20121,101.851.3%—
20131,531.171.5%—
20141,221.857.1%—
20151,269.759.3%—
201679136.9%—
20171,293.360.4%—
20181,267.659.2%—
2019712.433.3%—
20201,067.349.7%—
20211,573.873.5%—
20221,099.551.4%—
20231,121.252.4%—
20241,259.458.7%—
20251,294.660.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY4037.7Aug 1938Operating—coming soon
2Conventional HydroelectricHY4037.6Jun 1938Operating—coming soon
3Conventional HydroelectricHY4038.5Aug 1942Operating—coming soon
4Conventional HydroelectricHY4043.6Jun 1942Operating—coming soon
5Conventional HydroelectricHY4043.7Oct 1952Operating—coming soon
6Conventional HydroelectricHY4043.2Dec 1952Operating—coming soon

Owner / operator

Operator: Tennessee Valley Authority. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Tennessee Valley Authority100.0%240 MW

Nearby plants

Within 80 km.
Packaging Corp of America73 MW2.8 km
SR Adamsville25 MW23.6 km
Selmer I16 MW28.6 km
Selmer Farm LLC16 MW29.3 km
Mulberry Farm LLC16 MW31.5 km
Selmer II8 MW37.7 km