← Back to map

Roanoke Rapids

Halifax County, North Carolina · EIA plant ID 2758 · Operator: Virginia Electric & Power Co
HydroConventional HydroelectricPJMBA: PJM
Nameplate100MWSummer 98 MW
Generators4in service
Net generation187GWh12 mo to Dec 2025
Capacity factor22%hydro units, summer MW
Heat rate—thermal plants only
First online1955

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0204060GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020202521.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2001185.821.4%—
2002142.416.4%—
2003621.771.7%—
2004365.442.0%—
2005288.133.2%—
2006249.128.7%—
2007233.426.9%—
2008169.120.3%—
2009322.238.7%—
2010334.240.2%—
2011187.822.6%—
2012161.719.4%—
2013302.436.3%—
2014333.140.0%—
2015290.134.9%—
2016359.943.1%—
2017213.525.7%—
201837645.2%—
2019303.136.4%—
2020401.148.1%—
2021284.434.2%—
2022143.317.2%—
20236.70.8%—
2024271.732.6%—
2025187.221.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY2524.8Dec 1955Operating—coming soon
2Conventional HydroelectricHY2524.8Oct 1955Operating—coming soon
3Conventional HydroelectricHY2524.8Sep 1955Operating—coming soon
4Conventional HydroelectricHY2523.2Sep 1955Operating—coming soon

Owner / operator

Operator: Virginia Electric & Power Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Virginia Electric & Power Co100.0%100 MW

Nearby plants

Within 80 km.
KapStone Kraft Paper Corp28 MW2.8 km
Floyd Road Solar Farm5 MW3 km
Rosemary Power Station180 MW3.2 km
Gaston Solar5 MW4.2 km
Long Farm 46 Solar, LLC5 MW5 km
Halifax20 MW5.4 km