← Back to map

Sewalls

Jefferson County, New York · EIA plant ID 2608 · Operator: Erie Boulevard Hydropower LP
HydroConventional HydroelectricNYISOBA: NYIS
Nameplate2MWSummer 2 MW
Generators2in service
Net generation12GWh12 mo to Dec 2025
Capacity factor61%hydro units, summer MW
Heat rate—thermal plants only
First online1925

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.511.5GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020202560.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200113.677.6%—
200214.180.2%—
200315.186.0%—
20041.58.7%—
200514.473.3%—
200616.784.7%—
200710.959.4%—
200815.282.2%—
200913.573.5%—
201010.959.3%—
201113.774.4%—
201210.657.5%—
201313.469.7%—
201411.157.8%—
20156.433.3%—
20169.750.1%—
20171472.7%—
20187.639.3%—
20191577.6%—
202010.252.8%—
20211683.2%—
202214.675.5%—
202314.675.9%—
202415.178.1%—
202511.760.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY11.1Jan 1925Operating—coming soon
2Conventional HydroelectricHY11.1Jan 1925Operating—coming soon

Owner / operator

Operator: Erie Boulevard Hydropower LP. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Erie Boulevard Hydropower LP100.0%2 MW

Nearby plants

Within 80 km.
Diamond Island Plant1 MW0.7 km
Beebee Island Hydro Plant9 MW1 km
Watertown8 MW1.6 km
OYA Wayside Drive5 MW4.9 km
St. Lawrence University - Sutton2 MW5.3 km
Glen Park Hydroelectric Project33 MW5.9 km