← Back to map

Caro

Tuscola County, Michigan · EIA plant ID 1874 · Operator: Thumb Electric Coop of Mich
OilPetroleum LiquidsMISOBA: MISO
Nameplate9MWSummer 9 MW
Generators6in service
Net generation0GWh12 mo to Dec 2025
Capacity factor0%gas/coal/oil units, summer MW
Heat rate—Btu/kWhfossil units, electric fuel, HHV
First online1949Runs as rarely runs

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-60-40-200MWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%0%0%200520102015202020250.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
5,00010,00015,00020,00025,0002005201020152020
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20010.10.1%17,912
200200.0%13,297
200300.0%12,000
200400.0%21,667
200500.0%11,602
200600.0%—
2007-0.3-0.3%—
200800.0%—
200900.0%23,265
201000.0%23,667
201100.0%—
201200.0%—
201300.0%—
201400.0%—
201500.0%—
201600.0%13,848
201700.0%—
201800.0%16,156
201900.0%10,587
202000.0%—
202100.0%—
202200.0%—
202300.0%13,265
202400.0%—
202500.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Petroleum LiquidsIC1.31Aug 1949Operating—coming soon
2Petroleum LiquidsIC1.31Aug 1949Operating—coming soon
3Petroleum LiquidsIC1.31Aug 1952Operating—coming soon
4Petroleum LiquidsIC1.51.5Aug 1984Operating—coming soon
5Petroleum LiquidsIC22May 1999Operating—coming soon
6Petroleum LiquidsIC22Apr 2000Operating—coming soon

Owner / operator

Operator: Thumb Electric Coop of Mich. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Thumb Electric Coop of Mich100.0%9 MW

Nearby plants

Within 80 km.
POET Biorefining Caro, LLC4 MW6.8 km
Wilmot14 MW11.3 km
Pegasus Wind178 MW14.6 km
Tuscola Wind II LLC100 MW20.4 km
Cross Winds Energy Park231 MW20.5 km
Tuscola Bay Wind120 MW26.8 km