← Back to map

Cobble Mountain

Hampden County, Massachusetts · EIA plant ID 1630 · Operator: City of Holyoke Gas and Electric Dept.
HydroConventional HydroelectricISONEBA: ISNE
Nameplate33MWSummer 33 MW
Generators3in service
Net generation7GWh12 mo to Dec 2025
Capacity factor2%hydro units, summer MW
Heat rate—thermal plants only
First online1930

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-50510GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%200520102015202020252.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200130.911.3%—
200211.74.3%—
200325.19.3%—
200421.17.8%—
200529.210.8%—
200650.818.8%—
200722.98.4%—
200825.89.5%—
200924.88.7%—
201018.86.6%—
201134.712.2%—
201214.55.1%—
201321.87.6%—
201419.16.7%—
201518.76.6%—
201611.54.0%—
201710.73.7%—
201829.210.2%—
201921.17.4%—
202012.14.2%—
202120.87.3%—
20227.32.5%—
202310.53.7%—
20247.82.7%—
20257.12.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY1312.9Jan 1930Operating—coming soon
2Conventional HydroelectricHY76.8Jan 1930Operating—coming soon
3Conventional HydroelectricHY1312.9Jan 1930Operating—coming soon

Owner / operator

Operator: City of Holyoke Gas and Electric Dept.. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Springfield Water & Sewer Comm100.0%33 MW

Nearby plants

Within 80 km.
Russell (MA)3 MW5.5 km
International Paper Woronoco Mill3 MW6 km
Indian River Hydro1 MW7.8 km
Twiss Street Solar2 MW10.2 km
Holiday Hill Community Wind5 MW10.6 km
CED Westfield Solar, LLC2 MW11.1 km