← Back to map

Messalonskee 3

Kennebec County, Maine · EIA plant ID 1498 · Operator: Messalonskee Stream Hydro LLC
HydroConventional HydroelectricISONEBA: ISNE
Nameplate2MWSummer 2 MW
Generators1in service
Net generation4GWh12 mo to Dec 2025
Capacity factor27%hydro units, summer MW
Heat rate—thermal plants only
First online1918

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-0.2500.250.50.751GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202526.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2001-0-0.0%—
2002-0-0.1%—
2003-0-0.2%—
200400.0%—
200500.0%—
20067.452.6%—
20075.237.0%—
20088.862.7%—
20097.251.6%—
2010321.7%—
20116.848.7%—
20124.431.3%—
20136.848.8%—
20147.754.7%—
2015535.5%—
20164.330.4%—
20175.639.8%—
20184.935.1%—
20195.438.2%—
2020535.3%—
20214.230.0%—
20224.834.5%—
20237.352.0%—
20246.546.3%—
20253.826.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY1.61.6Jan 1918Operating—coming soon

Owner / operator

Operator: Messalonskee Stream Hydro LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Messalonskee Stream Hydro LLC100.0%2 MW

Nearby plants

Within 80 km.
Oakland5 MW0.8 km
Solar Mule, LLC2 MW1.6 km
Messalonskee 2 (Oakland)3 MW3.3 km
Cenergy - Waterville (CSG)5 MW3.6 km
Messalonskee 52 MW4.6 km
Webb Road Solar5 MW4.8 km