← Back to map

French Paper Hydro

Berrien County, Michigan · EIA plant ID 10656 · Operator: French Paper Co
HydroConventional HydroelectricPJMBA: PJM
Nameplate1MWSummer 1 MW
Generators4in service
Net generation1GWh12 mo to Aug 2026
Capacity factor12%hydro units, summer MW
Heat rate—thermal plants only
First online1921

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.511.5GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020202511.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20015.967.8%—
20025.664.1%—
20037.180.0%—
20048.481.3%—
20058.477.1%—
20069.787.0%—
20078.783.0%—
20086.965.9%—
20096.965.5%—
20108.177.1%—
20118.883.3%—
20128.277.4%—
20138.682.3%—
20147.773.4%—
20158.681.7%—
2016766.0%—
20176.157.8%—
20185.350.1%—
20194.845.4%—
20204.845.9%—
2021657.4%—
20224.341.1%—
2023547.2%—
20243.128.9%—
20252.624.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY0.30.3Jan 1922Operating—coming soon
2Conventional HydroelectricHY0.40.4Jan 1927Operating—coming soon
3Conventional HydroelectricHY0.40.3Jan 1930Operating—coming soon
4Conventional HydroelectricHY0.20.2Jan 1921Operating—coming soon

Owner / operator

Operator: French Paper Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
French Paper Co100.0%1 MW

Nearby plants

Within 80 km.
Southeast Berrien Generating Facility5 MW5.5 km
Indeck Niles Energy Center1,174 MW5.6 km
Buchanan (MI)4 MW7.9 km
University of Notre Dame40 MW12.5 km
Berrien Springs7 MW14.9 km
St. Joseph Solar20 MW16 km