← Back to map

DeRidder Mill

Beauregard County, Louisiana · EIA plant ID 10488 · Operator: Boise Packaging & Newsprint LLC
OtherWood/Wood Waste BiomassSPPBA: MISO
Nameplate62MWSummer 62 MW
Generators1in service
Net generation405GWh12 mo to Dec 2025
Capacity factor62%other units, summer MW
Heat rate4,637Btu/kWhfossil units, electric fuel, HHV
First online1969

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
010203040GWh200120042006200820102012201420162018202020222024

Capacity factor by year

Net MWh ÷ (summer MW × hours), other units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202561.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
4,0006,0008,000200520102015202020254,637 Btu/kWh · 12 mo
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2001416.860.5%8,741
2002472.165.3%8,479
2004397.561.8%5,165
2005385.661.9%5,010
2006384.663.9%5,165
2007375.661.5%5,165
2008363.360.2%5,165
2009306.752.7%5,165
2010332.857.1%5,165
2011339.657.2%4,811
2012352.559.7%4,811
2013375.465.0%4,811
2014376.664.2%4,811
2015377.159.9%5,165
2016408.262.0%4,637
2017398.165.6%4,637
2018387.660.2%4,637
2019382.652.1%4,637
2020385.454.6%4,637
2021376.149.7%4,637
202240758.6%4,637
202338957.8%4,637
2024402.460.4%4,637
2025404.561.9%4,637

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
TGWood/Wood Waste BiomassST61.561.5Oct 1969Operating—coming soon

Owner / operator

Operator: Boise Packaging & Newsprint LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Boise Packaging & Newsprint LLC100.0%62 MW

Nearby plants

Within 80 km.
Singer Solar—18.9 km
Fort Polk (fka Johnson) - Chaffee West5 MW31.5 km
Fort Polk (fka Johnson) - Chaffee East5 MW31.6 km
Elizabeth Solar Plant143 MW38.8 km
Toledo Bend81 MW39.2 km
Lake Charles Power1,000 MW62.9 km